Project Data
| Location | Abu Dhabi |
| Client | ADNOC |
| Products | Denso Bore-Wrap™ |
| Date | 2023 |
Project Details
ADNOC Sour Gas is a pioneer in sour gas field development and operates the world’s largest ultra-sour gas operation, with the capacity to produce 1.28 billion standard cubic feet of gas per day and 4.2 million tons of sulphur per year.
The project involves the Engineering, Procurement and Construction (EPC) contract for the Optimum Shah Gas Expansion (OSGE) & Gas Gathering project for the supply of materials, and the construction and commissioning of additional components, including a 24” diameter pipeline at the Shah Gas plant.
The expansion will optimise the plant, as well as improve both capacity and higher-end product recoveries, further growing contribution as a safe and reliable supplier of gas to ADNOC and the UAE.
Denso BoreWrap™ was selected as an Abrasion Resistant overlay to the 24” dia. FBE coated pipeline for three separate 110 meter long HDD applications at road crossings.

Application-of-the-Denso-abrasion-resistant-system-Denso-Bore-wrap-is-underway-on-pipeline

TO COMPLETE THE APPLICATION, DENSO™ POLY-WRAP IS APPLIEDOVERTHE DENSO BORE-WRAP AS ATEMPORARY CURING AID
Application-of-the-Denso-abrasion-resistant-system-Denso-Bore-wrap-is-underway-on-pipeline